A data center readiness review asks whether the facility can support its intended operating use now. It should consider systems, people, procedures, documentation, and unresolved issues. Construction completion and readiness are related milestones, but they are not identical.
Define the proposed operating condition first. State which phase, capacity, customer areas, and services are included. A partial opening needs a clear boundary so unfinished work does not become an unexamined dependency.
Review acceptance evidence by system and interface. Confirm completed tests, resolved defects, current settings, labels, and documentation. Identify conditions that were not demonstrated and assess their relevance to the proposed operation. Do not allow a large percentage-complete figure to obscure one essential unfinished interface.
Check the operating organization. Staff or service providers need access, training, procedures, escalation contacts, and the tools required for their responsibilities. Spare parts, maintenance arrangements, and emergency coordination should match the installed equipment.
Examine ongoing construction separately. Temporary routes, shared utilities, security boundaries, and future connections can affect the occupied phase. The operator should understand and accept the controlled arrangements.
Finish with a specific decision and an open-items register. Identify which issues prevent the proposed use, which can be managed under documented conditions, and who owns remaining work. A useful readiness review produces an evidence-based operating boundary, rather than a ceremonial approval that transfers unresolved construction problems to the people expected to run the facility.