Construction contingency should reflect the uncertainties still present in the project. There is no single percentage that can substitute for examining the site, design maturity, procurement plan, and owner's exposure to change.
Name the uncertainty
Begin with a risk discussion. Identify unresolved ground conditions, incomplete scope, uncertain equipment requirements, access restrictions, and other issues that could affect cost. Distinguish foreseeable but unpriced work from genuinely uncertain events; known missing scope belongs in the estimate.
Ask who carries each exposure under the proposed contracts. A contractor's contingency and an owner's reserve may cover different matters. Treating them as interchangeable can leave the owner assuming protection that the contract does not provide.
Tie the reserve to information
Suppose the foundation approach depends on an investigation not yet completed. Record that uncertainty and revisit it when the report and design are available. Some exposure may reduce, while a newly identified condition may become defined scope that needs to be budgeted directly.
The WBDG cost-management guidance links contingency decisions to project risk, including site and market conditions. That supports reviewing the reserve as the project develops rather than carrying an unexplained number unchanged.
Control its use
Establish who can authorize spending from the reserve and how it will be reported. A discretionary upgrade should be identified as an owner choice, not concealed as an unavoidable surprise.
Track the remaining reserve alongside forecast unresolved exposure. A contingency balance alone does not show whether the project is financially secure. The useful question is whether the available provision still matches the uncertainty remaining in the work, based on the best information currently available.